Solar panels (Part 14, Class A)
No permission needed
Likely permitted development, so no planning application
What to do next
To have it confirmed in writing, apply for a Lawful Development Certificate.
Conditions that apply (1)Siting.
- Place the panels to affect the look of the building and the area as little as possible, and take them down when they're no longer needed.(Part 14 A.2(a)–(c))
Rule checks
All 4 rule checks passed
- Protrudes ≤ 20cm15cm from the pitched roof
- Not above the highest part of the roofBelow the ridge (chimneys ignored)
- Not a listed buildingNo listing recorded
- No Article 4 DirectionNone recorded
Was this right?
What your project will cost
Sign in, free, to see build costs at your region’s rates, the saving from doing some of the work yourself, an all-in budget, and whether it’s likely to add value to your home.
Building Regulations
Separate from planning, and needed whether or not you apply for permission. 1 thing needs action.
- Part PNotifiable electrical workAction needed
Connecting panels to your consumer unit is notifiable. Use an MCS-certified installer. You'll need one anyway to be paid for electricity you export under the Smart Export Guarantee.
- Part ARoof or wall loading
The installer should confirm the roof or wall can carry the panels and wind loads.
PlanItClear is free while we launch. If it saved you a fee, you can support us.
Support PlanItClearPlanItClear is a screening tool, not legal advice. Check with your council, or get a Lawful Development Certificate, before you build. Costs are rough ranges. Data sources and licences. Report a problem with this result.
Which rules are checked
In England, the GPDO 2015 Schedule 2, Part 1 Classes A to E and Part 14 Class A, as amended to 27 August 2026. In Wales, the GPDO 1995 as it applies in Wales, Part 1 Classes A to E and Part 40 Class A. In Scotland, the GPDO (Scotland) 1992, Part 1 Classes 1A to 3A and Part 1A Class 6HA. In Northern Ireland, the GPDO (NI) 2015, Part 1 Classes A to D and Part 2 Classes A and B.