Do I need planning permission for rooflights in Wales?
Last updated 2 October 2026.
Check your own design
Enter your postcode and sizes to see whether your design is within these rules, and the most you can build.
The limits at a glance
- How far it stands out from the roof slopeOver 0.15m needs planning permission.
Worked out with the same rules as the checker, for a typical design. Your own limits may differ, depending on your home and plot.
The rules
- A rooflight can stand out no more than 15cm from the roof.
- No part can be higher than the highest part of the original roof.
- Rooflights on a side roof slope must be obscure-glazed and non-opening below 1.7m above the floor inside.
- Chimneys and flues aren’t covered by these rules, and solar panels have their own.
When the rules don't apply
- Conservation areas, National Parks, Areas of Outstanding Natural Beauty and World Heritage Sites: new rooflights need planning permission. In England they’re still allowed there.
- Listed buildings: rooflights need listed building consent.
- Article 4 Directions and flats: you’ll need planning permission.
New rooflights must meet current insulation standards, and cutting into the roof may need Building Regulations approval.
Common questions
Do I need a certificate to prove my rooflights don't need planning permission?
No, it's optional. A Lawful Development Certificate from your council confirms in writing that your plans are within the rules. It costs less than a planning application and is worth having for a bigger project, because a buyer's solicitor may ask for proof when you sell.
Can my neighbours object to my rooflights?
Not if they're within the permitted development rules: the council doesn't ask them, and there's no decision for them to object to. Separate rights still apply, such as covenants in your deeds and access to shared walls, so talk to them before work starts.
What if I've already fitted my rooflights without checking?
If they meet the rules, you don't need to do anything, though a Lawful Development Certificate for an existing use or development proves it. If not, you can apply for planning permission afterwards, and if that's refused, the council can make you change or remove the work. After a number of years the council can no longer act, and the same certificate can confirm that, so ask your council how the time limits apply.
Do I need planning permission to replace my windows?
Not usually, if the new windows look similar to the old ones. In a conservation area, an Article 4 Direction may mean new windows facing the road need permission, and a listed building needs listed building consent. Replacement windows must meet Building Regulations, which an installer registered with FENSA or CERTASS can certify for you.
Elsewhere in the UK
This guide covers Wales. Each UK nation has its own rules, similar in places but different in the detail.
Other guides
- Do I need planning permission for an extension in Wales?
- Do I need planning permission for a loft conversion in Wales?
- Do I need planning permission for a garden room in Wales?
- Do I need planning permission for a porch in Wales?
- Do I need planning permission for solar panels in Wales?
This guide explains the rules in general. It isn’t legal advice. For certainty about your own project, apply to your council for a Lawful Development Certificate.