Do I need planning permission for an extension?
Last updated 2 October 2026.
Check your own design
Enter your postcode and sizes to see whether your design is within these rules, and the most you can build.
The limits at a glance
- Single-storey rear, semi-detached or terraced houseOver 3m needs prior approval. Over 6m needs planning permission.
- Single-storey rear, detached houseOver 4m needs prior approval. Over 8m needs planning permission.
- Single-storey heightOver 4m needs planning permission.
- Two-storey rear, depthOver 3m needs planning permission.
- Two-storey rear, distance to the back boundaryUnder 7m needs planning permission.
Worked out with the same rules as the checker, for a typical design. Your own limits may differ, depending on your home and plot.
Single-storey rear extensions
Measured from the original back wall of the house, a single-storey rear extension can be up to 3m deep on a semi-detached or terraced house, and up to 4m on a detached house. It can be no more than 4m high.
Beyond that, up to 6m (or 8m for a detached house), you can build without planning permission if the council gives prior approval first. See how prior approval works.
“Original” means the house as it was first built, or as it stood on 1 July 1948 if it’s older. Earlier extensions count towards the limits, even ones built by a previous owner.
Two-storey extensions
An extension of more than one storey can go up to 3m beyond the back wall, and must be at least 7m from the boundary opposite it. There’s no prior approval route for anything bigger.
Upper-floor windows in a side wall must be obscure-glazed and non-opening below 1.7m above the floor, and the roof pitch should match the house as far as practical.
Side extensions
A side extension can be one storey, up to 4m high, and no wider than half the width of the original house. It can’t go beyond a side wall that faces a road, and on a terrace only the end houses can extend to the side.
An extension that wraps round the back and side has to meet the limits for both.
Rules for every extension
- It can’t be higher than the highest part of the existing roof, and its eaves can’t be higher than the house’s.
- Within 2m of a boundary, the eaves can be no more than 3m high.
- It can’t extend beyond the front of the house (its principal elevation).
- Extensions and other buildings together can cover no more than half the land around the original house.
- The outside materials should look similar to the existing house.
How prior approval works
For a single-storey rear extension between the standard and larger limits, you apply to the council before you build, with a plan and the extension’s size. The council writes to your neighbours, and if any object it decides whether the extension’s effect on their homes is acceptable. It’s quicker and cheaper than a planning application, but you mustn’t start until the council approves it, or the time for it to decide runs out.
Prior approval isn’t available in conservation areas, National Parks, National Landscapes or World Heritage Sites.
When the rules don't apply
- Conservation areas, National Parks, National Landscapes and World Heritage Sites: no side extensions, no extensions of more than one storey, and no cladding.
- Article 4 Directions: a council can remove permitted development rights in an area, so you’d need planning permission.
- Listed buildings: extensions need planning permission and listed building consent.
- Flats and maisonettes: these rules are for houses only.
- Earlier permissions: some planning permissions remove a home’s permitted development rights. Your council can tell you.
Whatever the planning answer, an extension you’ll live in needs Building Regulations approval, and work on or near a shared wall may need notice to your neighbours under the Party Wall etc. Act 1996.
Common questions
Do I need a certificate to prove my extension doesn't need planning permission?
No, it's optional. A Lawful Development Certificate from your council confirms in writing that your plans are within the rules. It costs less than a planning application and is worth having for a bigger project, because a buyer's solicitor may ask for proof when you sell.
Can my neighbours object to my extension?
Not if it's within the permitted development rules: the council doesn't ask them, and there's no decision for them to object to. The exception is a larger rear extension under prior approval, described above. Separate rights still apply, such as covenants in your deeds and access to shared walls, so talk to them before work starts.
What if I've already built my extension without checking?
If it meets the rules, you don't need to do anything, though a Lawful Development Certificate for an existing use or development proves it. If not, you can apply for planning permission afterwards, and if that's refused, the council can make you change or remove the work. After a number of years the council can no longer act, and the same certificate can confirm that, so ask your council how the time limits apply.
How long does prior approval take?
The council has 42 days from receiving a valid application, and your neighbours have 21 days of that to comment. If you haven't had a decision after 42 days, you can go ahead.
Does a conservatory count as an extension?
Yes. A conservatory or orangery follows the same planning rules as any other extension. It's usually exempt from Building Regulations if it's at ground level, under 30m² of floor area, separated from the house by outside walls, doors or windows, and heated separately or not at all. Its glazing must still be safety glass.
How much notice do my neighbours need under the Party Wall Act?
At least one month before building on or up to the boundary line, or before digging foundations close to their building, and two months before work on a shared wall itself. They can agree to the work or appoint a surveyor.
Elsewhere in the UK
This guide covers England. Each UK nation has its own rules, similar in places but different in the detail.
Other guides
- Do I need planning permission for a loft conversion?
- Do I need planning permission for a garden room?
- Do I need planning permission for a porch?
- Do I need planning permission for rooflights?
- Do I need planning permission for solar panels?
- Do I need planning permission for a fence?
- Do I need planning permission for a heat pump?
- Do I need planning permission for a driveway?
- Do I need planning permission for new windows and doors?
This guide explains the rules in general. It isn’t legal advice. For certainty about your own project, apply to your council for a Lawful Development Certificate.